Hotel FF&E lead times, counted backward
Count backward from opening day. Ocean freight to a typical port is several weeks, and a missed vessel is another week. Production of casegoods in volume is measured in weeks after the sample is signed, not after the first conversation.
The sample loop is the part teams under-budget. A finish that needs a second round, plus shipping the board to the designer, can consume a month before a single carcass is cut. Put that month on the schedule before you promise an opening.
Split the order if the public areas and the guestrooms are on different clocks. Seating with a graded-in fabric often waits on the fabric mill. Casegoods do not have to wait with it.